Access Flooring Site Requirements

Access floors should be installed in dry and watertight areas at a temperature above 40° and a humidity below 75 % RH. This is required for both the installation works and also for material storage.

 

Before installation, the subfloor must be in the following condition:

  • Free from wet or dry contamination.
  • Able to accept epoxy resin pedestal adhesive and if required mechanical fixings.
  • Any holes, joint lines etc in higher level sub floors should be sealed in order to prevent floor sealer leaking through to the level below.
  • The sub floor should be structurally strong enough to support the raised access floor and the environment it supports.
  • The sub floor is required to be structurally strong enough to allow the storage of raised floor materials prior to installation (note; palletized materials typically weigh 1200 lbs and stand 48" high and are 26" square).
  • The surface of the concrete sub floor should ideally be of a medium tamp finish in order to give a reasonably flat surface without inducing the formation of weak surface laitance.

Click here for more on Access Flooring!

 

General working conditions include:

  • Work areas to be free of other trades and their materials.
  • Adequate power supply to all work areas.
  • Adequate safety lighting to all work areas.
  • Work areas for the cutting of floor panels by the use of bandsaw.
  • Adequate means for the disposal of rubbish and debris.

Fieldmans Access Floors Ltd is a leading provider of raised access computer flooring in the UK. It has helped transform offices in very little time, and has given them the flexibility to make changes and stay competitive. For more information, please call 0208 462 7100 or write to Enquiries@Fieldmans.com.